(ANGM) Angel Mining
Summary
Trade long or short on this share now through an Interactive Investor Spread Bet or CFD
|
|
|||||||||||||||||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||
| Headline | Source | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 01-02-12 | RNS |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
RNS Number : 5355W Angel Mining PLC 01 February 2012 ANGEL MINING PLC ("Angel Mining" or the "Company") AIM: ANGM
ANOTHER RECORD GOLD POUR AND FINAL DRAWDOWN OF YORKVILLE PROMISSORY NOTE FACILITY
The Board of Angel Mining, the Greenland-focused mining, is pleased to provide the following update:
Nalunaq On Monday, 30 January 2012, a further 16.8 kilograms (539.9 ounces) of gold doré were successfully poured at Nalunaq. This is the largest single pour to date and shows continued progress towards the Company's target of between 1,500 and 2,000 ounces per month, which it hopes to achieve early this year.
During the three weeks since the last pour, the team lost approximately four days of production due to maintenance and repairs of the main generator. That aside, the team believe that gold recovery from the plant has now improved to c. 84%, a significant improvement over the levels achieved during the last few months of 2011.
Finance On 28 July 2011, the Company announced that it had entered into a promissory note with YA Global Master SPV Ltd ("Yorkville") up to a maximum value of $3,654,000. The initial drawdown under the note was $1,350,000 and the Company made a subsequent drawdown of $855,000. The Company has now fully drawn down on this facility. The outstanding balance of $3,654,000 will be repaid in a series of payments commencing on 8 March 2012 and finishing on 30 September 2012.
Nicholas Hall, CEO, commented: "The continued improvement in gold recovery and the associated increase in production levels indicate that the team is making important strides towards achieving our production target. The ongoing improvements to the process plant will further these efforts."
Enquiries:
Background to Angel Mining
Nalunaq
The Company first poured gold at Nalunaq on 27 May 2011 and had poured 103.4 kilograms (3,323.8 ounces) of gold doré by 31 December 2011. The Company is targeting optimal production by Q1 2012 of between 1,500 and 2,000 ounces per month, thereby providing the Company with cash flow which will be dedicated to funding development at Black Angel, further exploration at Nalunaq and reducing debt. The current mining plan anticipates a mine life of two to five years, subject to further exploration work. The directors anticipate that Nalunaq may enter into toll treatment arrangements with other potential gold mining activities in the region where appropriate. Angel Mining operates the only operational gold mine in the region and anticipates that its operation may be suitable for processing ore from other gold mining companies in the region.
Black Angel
The Black Angel project is a high grade zinc/lead project based around a previously developed mine in the north of Greenland. The table below sets out the JORC Code compliant mineral resources estimate for the Black Angel project which includes three sets of zones within the mine and three satellite deposits which have been explored.
The project consists of three phases:
Phase I: Complete the rehabilitation of infrastructure to allow access to the mine, the mine camp and related facilities.
Phase II: Complete the detailed review of the pillar extraction programme within the Angel and Cover Zones, including the construction of the process plant and related systems to allow for the shipment of concentrate from the site.
Phase III: Develop a further exploration programme for the existing JORC resources at the Ark and Glacier deposits as well as identified mineralization at Deep Ice, Nunngarut and a number of other exploration targets within the license area (see the announcements made by the Company on 6 June 2006 titled "Black Angel 2006 Resource Statement" and on 30 November 2007 titled "Black Angel 2007 Resource Statement").
This information is provided by RNS The company news service from the London Stock Exchange More |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 25-01-12 | RNS |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
RNS Number : 1510W Angel Mining PLC 25 January 2012 ANGEL MINING PLC ("Angel Mining" or the "Company") AIM: ANGM
Publication of Newsletter
The Board of Angel Mining is pleased to announce the publication of a corporate newsletter. The full wording of the newsletter can be found on the company's website (www.angelmining.com) but the summary text is as follows:
"Angel Mining's Company objectives for 2012 · Maximise the maintainable gold production at Nalunaq · Work smarter cost reduction programme · Develop a deliverable financing plan for Black Angel
Nalunaq
Production
As the initial stockpiles have begun to be depleted, production of ore from the mine has been ramped up, with tonnage and grades now sufficient to fully feed the process plant. The plant aims to increase its operational efficiency and reduce its costs by extending the interval between shipments. This will give the plant a longer, more regular processing cycle which will reduce chemical and energy consumption and reduce shipment costs of doré bars to the refinery whilst yielding the same amount of gold from fewer production cycles. Accordingly, the next pour of gold at Nalunaq is scheduled for Monday, 30th January.
The team needs to implement three more important improvements to the process plant before optimum performance can be achieved:
1. The throughput of the ball mill needs to be increased and this should now be possible as the new pinion, referred to in a previous update, has arrived on site. 2. A new pump, with a recessed impeller, is to be installed for the transfer of gold-loaded carbon between the CIP tanks and the elution circuit. The current pump damages the carbon and creates fines, which are lost to tailings resulting in the loss of some gold. We are currently out to enquiry for fast delivery. Once installed, this should permit Nalunaq to achieve the best recovery efficiency of gold that it can. 3. De-bottlenecking of the plant crushing circuit: the team is currently studying how to upgrade this section of the processing plant.
Cost Reduction
As the production process begins to settle into a routine and the team becomes better established, we have begun to identify areas where cost savings can be achieved. The main initial areas we are focusing on are; travel, administration, procurement of consumables and doré shipment costs.
New Ideas
Since commencing production, the mining team and the geologists have discovered that additional high grade ore may be accessible for processing and that the grade in the new development area of South Block is better than had been expected. As a result, we are refining our plans for new exploration drilling to try to extend the life of the mine.
Black Angel
Project Director
The recruitment of a Project Director for Black Angel continues. This is a crucial role and we are determined to find the best candidate possible. In the meantime, work is proceeding with support from Qualter Hall.
Site Planning Meeting
A site meeting was held at Black Angel for a week last autumn and significant progress was made with some fascinating new ideas emerging.
Qualter Hall and EMJ jointly designed the site layout at Maarmorilik to extend the camp, provide new fuel storage facilities, developed a covered store for concentrate awaiting shipment and operational consumables. The plan links buildings with the materials handling system to ensure efficient loading and unloading of cable car gondolas. They were also required to design a layout and operating system which will be as automated as possible to minimize the use of people and to cater for the very low winter temperatures. Golders and our team identified the ideal location for the mineral process plant as being inside the old workings and were able to determine the basics of ventilation and material handling.
Golders also examined the bulkhead that exists in the entrance to the Deep Ice Zone tunnel. As the tunnel is flooded, a well engineered plan will be required to work out how to safely remove the bulkhead so that access can be restored.
Perhaps the most interesting development, however, was the idea that the pillar entrapment mining method for safe pillar removal may be modified. Under this new plan, the pillars to be retained for roof support would be supported by a series of backfill walls, creating a honeycomb of voids which can then be used for the safe disposal of tailings. Golders need to complete a mining method report and model the new ideas but, at this stage, it is clear that the concept should benefit both CAPEX and operating costs whilst providing an environmentally safe repository for the tailings.
Financial Model
A new financial model is being prepared for the project based on cost data provided by GBM, Qualter Hall and EMJ. The CAPEX constituents reflect the work done in the autumn as referred to above but it is believed that a material reduction can be achieved by better sourcing of plant and equipment. Consequently, an exercise has begun to get more competitive supplier quotations and it is hoped that the revised cost data can be obtained within the next two months.
Finance
As reported in the last newsletter, every effort is being made to accelerate production of gold at Nalunaq to improve cashflow. Currently, the production is enabling the Company to meet its ongoing operating costs and as such the Company is working to reduce the backlog of supportive creditors.
People
Some kind shareholders presented the company with some bottles of champagne and that inspired a prize giving to members of the team who have made an exceptional contribution to the group in the last three months. The recipients of the prizes were:
1. Steve Ainsworth (Deputy GM and Head of Mining) for his contribution in transforming the mining team at Nalunaq 2. Joan Plant (Operations Support Manager) for developing a new control system to ensure that we are in total control of reports to the BMP (the Greenlandic regulatory authority) and with permit applications and renewals. Her work has been much praised by the BMP 3. Kevin McNair (CFO) for the effective management of cash through a period of great difficulty during which he was able to maintain the vital support of our suppliers.
"
Enquiries:
This information is provided by RNS The company news service from the London Stock Exchange More |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 11-01-12 | RNS |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
RNS Number : 3614V Angel Mining PLC 11 January 2012 ANGEL MINING PLC ("Angel Mining" or the "Company") AIM: ANGM
LARGEST SINGLE GOLD POUR TO DATE
The Board of Angel Mining, the Greenland-focused mining and exploration company, is pleased to announce that a further 16.1 kilograms (517.8 ounces) of gold doré was successfully poured at Nalunaq on Monday, 9 January 2012. This is the largest single pour to date and is another significant milestone as production continues to rise towards the target of between 1,500 and 2,000 ounces per month, which it hopes to achieve in early this year.
For the three weeks since the last pour the mine and plant operated with a skeleton crew over the holiday period and had to deal with very severe weather, which at points disrupted production. Access to the mine was hampered at times, due to blizzard conditions, as was access to fuel supplies from the harbor.
Nicholas Hall, CEO, commented: "I am delighted that the team have started 2012 with a record gold pour. This is the latest step in our steady increase in production at Nalunaq. In December 2011, Nalunaq reached the important milestone of becoming cash generative. We look forward to this cash generation continuing to improve in line with production.
"Photographs have been added to the photo gallery on the Company's website which helps gives some idea of the harsh conditions that the team have dealt with over the last few weeks."
Enquiries:
Background to Angel Mining
Nalunaq
The Company first poured gold at Nalunaq on 27 May 2011 and had poured 103.4 kilograms (3,323.8 ounces) of gold doré by 31 December 2011. The Company is targeting optimal production by Q1 2012 of approximately 24,000 oz per annum thereby providing the Company with cash flow which will be dedicated to funding development at Black Angel, further exploration at Nalunaq and reducing debt. The current mining plan anticipates a mine life of two to five years, subject to further exploration work. The directors anticipate that Nalunaq may enter into toll treatment arrangements with other potential gold mining activities in the region where appropriate. Angel Mining operates the only operational gold mine in the region and anticipates that its operation may be suitable for processing ore from other gold mining companies in the region.
Black Angel
The Black Angel project is a high grade zinc/lead project based around a previously developed mine in the north of Greenland. The table below sets out the JORC Code compliant mineral resources estimate for the Black Angel project which includes three sets of zones within the mine and three satellite deposits which have been explored.
The project consists of three phases:
Phase I: Complete the rehabilitation of infrastructure to allow access to the mine, the mine camp and related facilities.
Phase II: Complete the detailed review of the pillar extraction programme within the Angel and Cover Zones, including the construction of the process plant and related systems to allow for the shipment of concentrate from the site.
Phase III: Develop a further exploration programme for the existing JORC resources at the Ark and Glacier deposits as well as identified mineralization at Deep Ice, Nunngarut and a number of other exploration targets within the license area (see the announcements made by the Company on 6 June 2006 titled "Black Angel 2006 Resource Statement" and on 30 November 2007 titled "Black Angel 2007 Resource Statement").
This information is provided by RNS The company news service from the London Stock Exchange More |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 04-01-12 | RNS |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
RNS Number : 9391U Angel Mining PLC 04 January 2012 ANGEL MINING PLC (the "Company") AIM: ANGM
TOTAL VOTING RIGHTS
For the purposes of the Financial Services Authority's Disclosure and Transparency Rules, the total number of Ordinary Shares in issue is 903,652,850 with each share carrying the right to one vote. In addition, the Company also has one B Share of GBP1 in issue which carries 577,275,625 voting rights in the Company. There are no shares held in treasury. Therefore, the total number of voting rights in the Company is 1,480,928,475. This figure may be used by shareholders in the Company as the denominator for the calculations by which they will determine if they are required to notify their interest in, or a change to their interest in, the share capital of the Company under the Disclosure and Transparency Rules.
Enquiries:
This information is provided by RNS The company news service from the London Stock Exchange More |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
They have not been approved or issued by Interactive Investor Trading Limited.
Editor's Pick:
What's in store today...Editor's Pick:
Glenstrata's just a silly word. Stick to big dividendsEditor's Pick:
Bulls should head for ChinaEditor's Pick:
Stock to Watch: Imperial TobaccoEditor's Pick:
George Godber’s AIM stock picks

